1. Ajmal alone can complete a work in 16 days and Basu alone can do in 12 days. Starting with Ajmal, they work on alternate days. The total work will be completed inba) 13 1/4 days b) 13 1/2 days c) 13 3 days d) 14 days |
|
Answer» a 13 15 dayssExplanation:because AJMAL is more STRONGER than BASU |
|