15 men can do a work in 330 days. But after 220 days 15 more people are recruited, then in how many more days the work will be completed?A. 80 daysB. 60 daysC. 55 daysD. 50 days1. D2. C3. B4. A

Answer» Correct Answer - Option 2 : C

Given:

M1 = 15, D1 = 330 days

M2 = 15 + 15 = 30

Concept used:

Total work = Number of men × Total number of days

Calculation:

Let x more days to complete the remaining work after 220 days.

Total work = Number of men × Total number of days

Total work = M1 × D1 

Total work = 15 × 330

Total work = 4950

Work completed after 220 days = 15 × 220

Required work = 3300

Remaining work = Total work – Work completed after 220 days

⇒ Remaining work = 4950 – 3300

⇒ Remaining work = 1650

Remaining work = M2 × x

⇒ 1650 = 30 × x

⇒ x = 55

∴ 55 more days the work will be completed.