39. P can completeof a work in10 days, g can complete 40% ofthe same work in 15 days, R,completes of the work in 13days and S. of the work in 736days. Who will be able to complete the work first? |
|
Answer» Given that P can do 1/4 of work in 10 days10 days = 1/4 of the work1 day = 1/4 ÷ 10 = 1/40 of the workP can do whole work in 40 days Given Q can do 40% of the work in 15 days15 days = 40/100 of the work1 day = 40/100 ÷ 15 = 2/75 of the work Q can do whole work in 37.5 days Given that R can do 1/3 of the work in 13 days13 days = 1/3 of the work1 day = 1/3 ÷ 13 = 1/39 of the workR can complete whole work in 39 days Given that S can do 1/6 of the work in 7 days7 days = 1/6 of the work1 day = 1/6 ÷ 7 = 1/42 of the workS can complete whole work in 42 days Therefore, Q will complete the work first |
|