45 men can finish a task in 16 days. After 6 days, 30 more men join them. How manydays, will they all, now take to complete the remaining task? |
|
Answer» Let total days they take to complete remaining task be x As amount of work remain same. Thus, 45*16 = 45*6 + (45+30)*x45(16 - 6) = 85*x75x = 450x = 450/75x = 6 Therefore, remaining task will be completed in 6 days |
|