A 66.6% risk is considered as(a) very low(b) low(c) moderate(d) highThe question was asked in a job interview.My doubt stems from Project Management in division Software Management of Software Engineering

Answer»

The CORRECT choice is (d) high

Easiest explanation: The PROBABILITY of the RISK might be assessed as very low (<10%), low (10–25%), moderate (25–50%), high (50–75%), or very high (>75%).