| 1. |
A and B can complete a piece of work in 12 days and 18 days respectively. They start working but 3 days before the completion of work, A left. In how many days will the total piece of work be completed?1. 9 days2. 6 days3. 7 days4. 5 days |
|
Answer» Correct Answer - Option 1 : 9 days Given: A and B can complete a piece of work in 12 days and 18 days respectively. A left before 3 days from the completion of work. Concept used: Time = Work/Efficiency Calculation: A's 1 day work = 1/12 B's 1 day work = 1/18 (A and B)'s 1 day work = [(1/12) + (1/18)] ⇒ 5/36 As B alone worked for last 3 days, ⇒ B's 3 days work = 3/18 = 1/6 Remaining work = 1 – (1/6) = 5/6 Remaining work is done by A and B together. Time = Work/Efficiency ⇒ Time = (5/6) ÷ [(1/18) + (1/12)] ⇒ (5/6) ÷ (5/36) ⇒ 6 days. Total days taken by to complete aa piece of work = 6 days + 3 days ⇒ 9 days. ∴ A and B took 9 days to complete a piece of work. |
|