A, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?A. 65 daysB. 76 daysC. 95 daysD. 190 days |
|
Answer» Correct Answer - D (i) The ratio of capacities of A,B and C is `10:5:4`. (ii) Find the time taken by A,B and C together to complete the work (say d) (iii) When they are taking d days, C alone takes 25 days. (iv) Find the how many C alone takes if they complete the work in 40 days. |
|