1.

A, B, and C can do a piece of work in 15 days, 18 days, and 24 days respectively. They started work together, but after 5 days A left the work, B left the work 6 days before the completion of the work. In how many days the work gets completed?1. \(10\frac{2}{7}\)2. \(10\frac{6}{7}\)3. \(8\frac{4}{5}\)4. \(11\frac{2}{7}\)

Answer» Correct Answer - Option 1 : \(10\frac{2}{7}\)

Given:

A can do a piece of work = 15 days

B can do a piece of work = 18 days

C can do a piece of work = 24 days

Calculations:

Let the total work done be in 'x' days

A's one day's work = 1/15

A worked for 5 days = 1/3

A can do 1/3 of work in 5 days

B's one day work = 1/18

B's (x - 6) days work = (x - 6)/18

C's one day work = 1/24

C's 'x' days work = x/24

(A + B + C) together work = 1

⇒ 1/3 + (x - 6)/18 + x/24 = 1

⇒ (24 + 4x - 24 + 3x)/72 = 1

⇒ 7x = 72

⇒ x = 72/7

⇒ x = \(10\frac{2}{7}\)

∴ The number of days together is \(10\frac{2}{7}\)  days



Discussion

No Comment Found

Related InterviewSolutions