1.

A, B and C can individually complete a task in 20 days, 15 days and 12 days, respectively. A started the work and left after some days. After this B and C worked for 3 days and completes the work. Then find for how many days A has worked in the beginning?1. 11 days2. 9 days3. 13 days4. 15 days

Answer» Correct Answer - Option 1 : 11 days

Given:

A, B, and C takes 20 days, 15days, and 12 days respectively.

B and C worked for 3 days.

Formula Used:

Total work is the LCM of time taken

Efficiency = Total work/Time taken

Calculation:

Total units of work = LCM of 20, 15, and 12

⇒ Total units of work = 60 units

Efficiency = Total work/Time taken

EfficiencyA = 60units/20days

⇒ EfficiencyA = 3 units/day

EfficiencyB = 60units/15days

⇒ EfficiencyB = 4 units/day

EfficiencyC = 60units/12days

⇒ EfficiencyC= 5 units/day

B and C worked for 3 days.

Total units of work completed by them,

⇒ Units of work completed = (B + C) × 3 days

⇒ Units of work completed = (4 + 5) × 3

⇒ Units of work completed = 9 × 3

⇒ Units of work completed = 27 units

Remaining units of work = 60 – 27

⇒ Remaining units of work = 33 units

33 units of work completed by A in the starting days.

⇒ Number of Days taken A = 33/3

⇒ Number of Days taken A = 11 days

∴ The number of days A worked for is 11 days. 



Discussion

No Comment Found

Related InterviewSolutions