1.

‘A’ can complete a piece of work in 12 days. ‘A’ and ‘B’ together can complete the same piece of work in 8 days. In how many days can ‘B’ alone complete the same piece of work?(a) 15 days (b) 18 days (c) 24 days (d) 28 days (e) None of these

Answer»

(c) Number of days = 12x8/12-8

= 24 days