A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together? |
|
Answer» One day work of A and B`=(1)/(9)+(1)/(12)=(7)/(36)` So they can complete work in `(36)/(7),i.e.,5(1)/(7)`days. |
|