1.

A can do one-third of a piece of work in 4 days and B can do one-fourth of the work in 6 days. How long will they take to complete the work, working together ?A. 12 daysB. 6 daysC. 8 daysD. 10 days

Answer» Correct Answer - C
Find the part of the work done by A and B individually in 1 day.