A Company Contracts To Paint 3 Houses. Mr.brown Can Paint A House In 6 Days While Mr.black Would Take 8 Days And Mr.blue 12 Days. After 8 Days Mr.brown Goes On Vacation And Mr. Black Begins To Work For A Period Of 6 Days. How Many Days Will It Take Mr.blue To Complete The Contract? |
|
Answer» 11. 11. |
|