A company estimated the manufacturing overhead costs for 2018 at $420,000. The total estimated direct labor hours are 15,000 hours, and the estimated machine hours to be worked are 6,000 hours. The actual labor hours were 16,500 hours and the overheads account had the debit balance of $450,000. Compute the over or under allocated manufacturing overheads for 2018? a. $12,000 under-allocated b. $12,000 over-allocated c. $68,182 over-allocated d. $68,182 under-allocated |
| Answer» ANSWER was very DIFFICULT but I KNOW this is answer is I am only in this 6TH CLASS | |