1.

A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number of lines of code (LOC) developed using L2 is estimated to be twice the LOC developed with Ll. The product will have to be maintained for five years. Various parameters for the company are given in the table below.ParameterLanguage L1Language L2Man years needed for developmentLOC/10000LOC/10000Development cost per man yearRs. 10,00,000Rs. 7,50,000Maintenance time5 years5 yearsCost of maintenance per yearRs. 1,00,000Rs. 50,000Total cost of the project includes cost of development and maintenance. What is the LOC for L1 for which the cost of the project using L1 is equal to the cost of the project using L2?(A) 10,000(B) 5,000(C) 7,500(D) 75,000