1.

A contractor undertakes to complete the construction of a tunnel 720 meters long in 240 days and employs 60 men for the purpose. After 120 days, he finds that only 240 meters of the tunnel is complete

Answer»

60 men



In 120days, only 240m of the TUNNEL is constructed by 60 men.
The REMAINING 120days, 480m of the tunnel can be constructed by 120 men.
Additional number of men required = 120 - 60 = 60 men.