A is five times as efficient as B. A can complete a work in 60 days less than B. If both of them work together then in how many days the work would be completed?1. 10.5 days2. 11.5 days3. 12 days4. 12.5 days |
|
Answer» Correct Answer - Option 4 : 12.5 days Given: The efficiency of A = 5 × the efficiency of B Then ratio of efficiency of A to the efficiency of B = 5 : 1 A can complete a work in 60 days less than B. Concept used: Days is inversely proportional to efficiency If A does a work in x days and B does a work in y days, the ratio of days = x : y and The ratio of efficiency = y : x If a person does a work in ‘n’ days then one day work by a person will be 1/n part of total work Calculation: Let the efficiency of A and B be 5x and x respectively. Then the number of days taken by A and B for a work will be x and 5x respectively A takes less time than B = 5x – x ⇒ A – B = 4x days According to question, A – B = 60 days ⇒ 4x = 60 ⇒ x = 60/4 ⇒ x = 15 Then A takes days to complete a work = x ⇒ 15 days Now one day work by A = 1/15 B takes days to complete a work = 5x ⇒ 5 × 15 ⇒ 75 days Now one day work by B = 1/75 One day work when both work together = one day work by A + one day work by B ⇒ 1/15 + 1/75 ⇒ (5 + 1)/75 ⇒ 6/75 ⇒ 2/25 ⇒ 1/12.5 Now, one work completed by both A and B = 12.5 days ∴ The work would be completed by both in 12.5 days |
|