Saved Bookmarks
| 1. |
A is twice efficient of B. If A takes 60 days less than B, then how many days required to complete work. When they work together?1. 30 days2. 50 days3. 40 days4. 20 days5. None of these |
|
Answer» Correct Answer - Option 3 : 40 days Given: Efficiency ratio of A and B = 2 ∶ 1 Condition = A takes 60 days less than B Formula: W = E × T Here, W = work E = Efficiency T = Time Calculation: We know that – E ∝ 1/T (w = constant) Efficiency Ratio of A & B = 2 : 1 Days Ratio of A & B = 1 : 2 Now, 2 – 1 = 60 1 = 60 Now, A = 1 ×60 A = 60 days B = 2 ×60 B = 120 Now, LCM (60, 120) = 120 unit Efficiency of A and B together = 2 + 1 = 3 Required time = 120/3 Required time = 40 days ∴ They completed the work together in 40 days. |
|