A person has undertaken a construction job. The probablities are 0.65 that will be strike, 0.80 that the constructionjob will becompleted on timeif there is no strike, and 0.32 thatthe construction job will be completed on time if there is a strike. Then the probability that the construction job will be completed on time is |
|
Answer» `0 . 788` |
|