1.

A PERT network is activity-oriented while a CPM network is event-oriented.(a) True(b) FalseThe question was asked in exam.This key question is from PERT and CPM topic in division Building Plans, PERT and CPM of Construction & Building Materials

Answer»

Right ANSWER is (B) False

The best explanation: A CPM network is ACTIVITY-oriented while a PERT network is event-oriented. Event is the completion of an activity or the commencement of an activity. An event may be head event, TAIL event or dual role event.