Saved Bookmarks
| 1. |
A PERT network is activity-oriented while a CPM network is event-oriented.(a) True(b) FalseThe question was asked in exam.This key question is from PERT and CPM topic in division Building Plans, PERT and CPM of Construction & Building Materials |
|
Answer» Right ANSWER is (B) False |
|