1.

A pre-timed three phase signal has critical lane flow rate for first two phases as 300,278 veh/hr with saturation flow rate as 1800veh/hr/land for all phases. The lost time is 5 seconds for each phase. If cycle length is 60 seconds, then the effective green time of the third phase is seconds.18.35

Answer» A pre-timed three phase signal has critical lane flow rate for first two phases as 300,278 veh/hr with saturation flow rate as 1800veh/hr/land for all phases. The lost time is 5 seconds for each phase. If cycle length is 60 seconds, then the effective green time of the third phase is seconds.
  1. 18.35