A project usually has a timeline chart which was developed by(a) Henry Gantt(b) Barry Boehm(c) Ivar Jacabson(d) None of the mentionedI have been asked this question at a job interview.This interesting question is from Project Scheduling and Tracking in chapter Software Management of Software Engineering |
|
Answer» Right ANSWER is (a) Henry Gantt |
|