InterviewSolution
Saved Bookmarks
| 1. |
A reactor has feed from 2 streams, one with rate 10 Kg/hr and other with 30 Kg/hr, and product side also has 2 streams one of which is at the rate of 15 Kg/hr, what is the rate of other product stream?(a) 5 Kg/hr(b) 15 Kg/hr(c) 25 Kg/hr(d) 35 Kg/hrI had been asked this question in an interview.My question is taken from Multiple Component Systems topic in chapter Introduction to Material Balances of Basic Chemical Engineering |
|
Answer» Correct choice is (C) 25 Kg/hr |
|