'A' takes 6 days less than the time taken by 'B' to finish a piece of work. If both A and B together can finish it in 4 days, find the time taken by 'B' to finish the work. (1) 2 days (2) 12 days (3) 6days (4) 10 days |
|
Answer» Correct Option is (2) 12 days |
|