A technique for performing quantitative analysis of progress is known as(a) BCWS(b) EVA(c) BAC(d) CBSEI got this question during a job interview.I would like to ask this question from Project Scheduling and Tracking topic in chapter Software Management of Software Engineering

Answer»

Correct answer is (b) EVA

The EXPLANATION is: The earned value system provides a common value scale for every task, regardless of the type of work being PERFORMED. The total hours to do the WHOLE PROJECT are estimated, and every task is given an earned value based on its estimated percentage of the total.