1.

A work measurement study was carried out in a firm for 10hrs and the following information was generated: Unit produced -350, idle time-15%, performance rating- 120% , allowance time 10% of standard time. What is standard time for the task?

Answer»

Answer:

Ok Good QUESTION

Explanation:

(iii) A work measurement study was carried out in a firm for 10 hours and the ... Answer: Calculation of STANDARD time for task ... Units produced 700; Idle time 15% ; PERFORMANCE rating 120%; allowance time 10% of.