Acan do a work in 21 days. B is 40%more good as A. In how much time Bcomplete the work?(A) 10(C) 24(B) 15(D) 28

Answer»

one day work of A = 1/21B is 40 % more efficient than A which means that A will take 40% more days than B because efficiency and number of days are inversely proportional to each other.

=> 21 is 40% more than B’s days.

=> 21 = (140/100)*B’s days

=> B’s days = 21*(100/140) = 15 days