1.

Arun and Satyam can complete a work individually in ,12 working days and 15 working days respectively with their full efficiencies. Arun does work only on Monday, Wednesday and Friday while Satyam does the work on Tuesday, Thursday and Saturday. Sunday is always off. But Arun and Satyam both works with half of their efficiencies on Friday and Saturday respectively. If Arun started the work on 1st January which falls on Monday followed by Satyam on the next day and so on (i.e., they work collectively in alternate days), then on which day work will be completed?

Answer»

Tuesday
Wednesday
Thursday
Friday

Answer :C