1.

At a hydroelectric power plant, the water pressure head is at a height of 300 m and the water flow available is 100 m3s−1. If the efficiency of the AC generator, coupled with the turbine, is 60%, estimate the electric power available from the plant.Take, g=9.8 ms−2

Answer»

At a hydroelectric power plant, the water pressure head is at a height of 300 m and the water flow available is 100 m3s1. If the efficiency of the AC generator, coupled with the turbine, is 60%, estimate the electric power available from the plant.



Take, g=9.8 ms2