1.

Calculate the Prime cost from the following data:Direct material RS 24,000, Direct labour RS 15,000, Direct expenses RS 12,000, Power and fuel RS 4,500, Office stationery RS 6,100, Office telephone charges RS 9,200.

Answer»

Prime Cost = Direct material + Direct labour + Direct expenses

= 24,000 + 15,000 + 12,000

= RS 51,000