Calculate the Prime cost from the following data:Direct material 12,000, Direct labour 5,000, Direct expenses 2,000, Power and fuel 3,500, Office stationery 1,100, Office telephone charges 200.

Answer»

Prime Cost = Direct material + Direct labour + Direct expenses

= 12,000 + 5,000 + 2,000

= RS 19,000