Can You Manually Generate A Purchase Requisition Referencing A Purchase Order Or A Scheduling Agreement?

Answer»

A Purchase Requisition cannot be created with reference to either of these, as they are documents controlled by the purchasing organizations.
Requirements can be AUTOMATICALLY generated with MRP that reference a SCHEDULING AGREEMENT if the SOURCE list is maintained for item-vendor combination.

A Purchase Requisition cannot be created with reference to either of these, as they are documents controlled by the purchasing organizations.
Requirements can be automatically generated with MRP that reference a Scheduling Agreement if the source list is maintained for item-vendor combination.