Answer» The planning process flow describes the business process and the TECHNICAL system process that are involved in CBP. The system accomplishes the following partial processes in the planning run:
1. The system first checks the planning file entries and also checks whether or not the material is changed in the planning run.
2. The system accomplishes a net requirement calculation for EVERY material. It checks whether, or not the requirement quantity is covered by available warehouse stock.
3. After CARRYING out a net requirement calculation for every material, the system then carries out the log-sizing calculation.
4. The scheduling is done for the start and finish dates of the procurement proposals.
5. The system determines the type of procurement proposals and creates planned orders, purchase requisitions, or schedule lines for the materials.
6. The system creates exception messages and accomplishes a rescheduling check to recognize critical situations of the planner that has to be PROCESSED manually in the planning results.
7. The system also computes the actual days SUPPLY and the receipt days supply of the materials. The planning process flow describes the business process and the technical system process that are involved in CBP. The system accomplishes the following partial processes in the planning run:
1. The system first checks the planning file entries and also checks whether or not the material is changed in the planning run.
2. The system accomplishes a net requirement calculation for every material. It checks whether, or not the requirement quantity is covered by available warehouse stock.
3. After carrying out a net requirement calculation for every material, the system then carries out the log-sizing calculation.
4. The scheduling is done for the start and finish dates of the procurement proposals.
5. The system determines the type of procurement proposals and creates planned orders, purchase requisitions, or schedule lines for the materials.
6. The system creates exception messages and accomplishes a rescheduling check to recognize critical situations of the planner that has to be processed manually in the planning results.
7. The system also computes the actual days supply and the receipt days supply of the materials.
|