_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.(a) Supplementary and revised estimate(b) Maintenance estimate(c) Item rate estimate(d) Revised estimate |
|
Answer» Correct answer is (b) Maintenance estimate The explanation is: For building; this includes white washing, colour washing, painting, minor repairs etc. For road works the A.R. estimate provides for patch repairing, renewals, repair of culverts, etc. |
|