_______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.(a) Supplementary and revised estimate(b) Maintenance estimate(c) Item rate estimate(d) Revised estimate

Answer» Correct answer is (b) Maintenance estimate

The explanation is: For building; this includes white washing, colour washing, painting, minor repairs etc. For road works the A.R. estimate provides for patch repairing, renewals, repair of culverts, etc.