Importance :

  • It is an ambitious multipurpose river valley project in Odisha, planned for harnessing the waters of Mahanadi river.
  • There dams are constructed across the Mahanadi at different places. 
  • The 4801 mt long dam has been built across the Mahanadi at Hirakud, 9.7 kms up stream of Sambalpur. 
  • The height of the dam above the river bed is 61 metres. 
  • It is the longest dam in India and forms 650 km2 reservoir. 
  • It has a gross storage capacity of 810 crore cubic meters of water. 
  • They irrigate 2.54 lakh hectares. 
  • The project has two hydro-electric power stations with an installed capacity of 270 m. 
  • The second and third dams are constructed at Tikarapara and Naraj respectively. 
  • The Mahanadhi Delta Irrigation scheme can provide irrigation for 6.84 lakh hectares. 
  • The third one comprises of 1353 km and 386.2 km long canals with irrigation potential of 5.4 lakh hectares. 
  • Chief Aims of this projects are :
  • Flood control 
  • Irrigation development 
  • Generation of hydro-electric power 
  • Provides navigation, recreational facilities and afforestation.