InterviewSolution
Saved Bookmarks
| 1. |
For complete hydration of cement the w/c ratio needed is ________(a) More than 0.25(b) More than 0.25 but less than 0.35(c) More than 0.35 but less than 0.60(d) More than 0.60I have been asked this question in an internship interview.I need to ask this question from Process of Manufacture of Fresh Concrete topic in division Fresh Concrete of Concrete Technology |
|
Answer» Right answer is (c) More than 0.35 but LESS than 0.60 |
|