For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.(a) True(b) FalseThis question was addressed to me in exam.This key question is from Types of Estimates topic in division Rate Analysis, Estimation and Costing of Construction & Building Materials

Answer»

The correct choice is (a) True

To explain: For the preparation of approximate estimates, CUBICAL contents METHOD is more ACCURATE than the UNIT base method and plinth area method. Cubical contents method is usually USED for multi-storeyed buildings.