| 1. |
For walls, columns and vertical faces of all structural members, the form work is generally removed after __________(a) 24 to 48 hours(b) 3 days(c) 7 days(d) 14 daysThe question was posed to me during an interview.Question is from Advantages of Quality Control topic in section Quality Control of Concrete Technology |
|
Answer» Correct choice is (a) 24 to 48 HOURS |
|