From the past data the indices were calculated for money in circulation and cost of living |
|
Answer» Hey mate your answer is Cement Masters has entered an agreement with Meadow Golf Club to construct a new path for $200,000. With this agreement is a potential bonus payment of $40,000. This performance bonus is will be paid in full if the project is COMPLETED by the agreed UPON date. Otherwise, the payment amount will decrease by $10,000 PER week for each week beyond the agreed upon date. Experience by Cement Masters' project manager leads him to estimate that there is a 55% probability the project will complete on time, a 30% probability the project will be 1 week late, and 15% probability the project will complete 2 WEEKS LATER than the agreed upon date. Hope this helps Mark as BRAINLIEST ♥️ |
|