Harish is 50% more efficient than Rajesh. If Rajesh can do 26 percent of the work in 13 days, find the time taken to finish the work when both works together.1. 60 days2. 50 days3. 40 days4. 30 days5. 20 days

Answer» Correct Answer - Option 5 : 20 days

Given:

Harish is 50% more efficient than Rajesh.

Rajesh does 26% of work in 13 days.

Concept used:

Work done = Time × Efficiency

Calculation:

Number of days taken by Rajesh = 13 × 100/26 = 50 days

The ratio of efficiency of Harish to Rajesh = 3 ∶ 2

Work done

Time taken

Efficiency

Harish

100/3

3

Rajesh

50

2

Total work

50 × 2 = 100


Time taken by both of them together to finish the work = 100/(3 +2) = 20 days

Time taken by both to finish the work together is 20 days.