How is plan driven development different from agile development ?(a) Outputs are decided through a process of negotiation during the software development process(b) Specification, design, implementation and testing are interleaved(c) Iteration occurs within activities(d) All of the mentionedI had been asked this question during a job interview.This key question is from Agile Software Development topic in chapter Software Processes, Models and Agile Software Development of Software Engineering

Answer»

Right option is (c) Iteration OCCURS WITHIN activities

To explain I WOULD say: A plan-driven approach to SOFTWARE engineering is based around separate development stages with the outputs to be PRODUCED at each of these stages planned in advance.