1.

How many phases are there in Scrum ?(a) Two(b) Three(c) Four(d) Scrum is an agile method which means it does not have phasesThe question was posed to me by my school principal while I was bunking the class.The above asked question is from Agile Software Development in division Software Processes, Models and Agile Software Development of Software Engineering

Answer»

Correct answer is (b) THREE

The BEST explanation: There are three phases in Scrum.The INITIAL phase is an outline planning phase followed by a SERIES of sprint cycles and project closure phase.