If 10 persons can do a job in 20 days. Then 20 persons with the twice efficiency can do the same job in:1. 152. 103. 54. 20 |
|
Answer» Correct Answer - Option 3 : 5 Given: 10 person complete a work in 20 days Formula used: Total work = Time × Efficiency × Men Calculation: Let efficiency of men be 'a'. and the time is taken to complete the work be 'w' Total work = Time × Efficiency × Men ⇒ Total work = 20 × a × 10 ----(i) Now after work efficiency is doubled Total work = Time × Efficiency × Men ⇒ Total work = w × 2a × 20 ----(ii) equating equation 1 and 2 ⇒ 20 × a × 10 = w × 2a × 20 ⇒ w = (20 × a × 10)/(2a × 20) ⇒ w = 5 ∴ 20 persons will complete the same work in 5 days. |
|