If 12 men or 24 boys can do a work in 30 days, the number of days in which 15 men and 6 boys can do it is1. 202. 453. 354. 16 |
|
Answer» Correct Answer - Option 1 : 20 Given: 12 men or 24 boys can do a work in 30 days. Calculations: Let the amount of work done by 1 man in 1 day be M. and the amount of work done by 1 boy in 1 day be B. according to the question, 12 × M × 30 = 24 × B × 30 so M ∶ B = 2 ∶ 1 so total amount of work = 24 × 1 × 30 = 24 × 30 now work done by 15 men and 6 boys in 1 day = 15 × 2 + 6 × 1 = 36 so the number of days taken by 15 men and 6 boys to complete the work = (24 × 30)/36 = 20 days ∴ the correct answer is 20 days. |
|