| 1. |
If 30 labourers working 7 hours a day can finish a piece of work in 18 days, how many labourers working6 hours a day can finish it in 30 days? |
|
Answer» As 30 labours complete work in 18*7 hours=126 hours let x labours nedded to complete work in =6*30=180hours This is case of inverse variation, So, 30*126=x*180 x=30*126/180=21 labours |
|