Saved Bookmarks
| 1. |
If 36 persons are engaged on a piece of work, the work can be completed in 40 days. After 32 days, only 3/4 th of the work was completed. How many more persons are required to complete the work on time?1). 102). 83). 94). 12 |
|
Answer» Solution Remaining work = $\FRAC{1}{4}$ |
|