| 1. |
If 60 engineers of 120 doctors or 100 teachers can finish a work in 360 days then in how many days will 10 engineers, 40 doctors and 50 teachers working together will complete the same work? |
|
Answer» 360 days ALSO `10E+40D+50T= 1/6 + 1/3 + 1/2 unit = 1 unit` Therefore 10 engineers, 40 doctors and 50 teachter working together will complete the same work in same TIME i.e. 360 days. |
|