In a cavity wall, the space between the leaves should be filled with a material which is not __________(a) Waterproof(b) Load-bearing(c) Non-load bearing(d) InsulatingThe question was asked in a job interview.My question comes from Types of Walls in section Load Bearing Walls of Construction & Building Materials

Answer»

Right choice is (b) Load-BEARING

The explanation: In a cavity wall, the space between the leaves or the cavity should be filled with a MATERIAL that is highly insulating, WATERPROOF and non-load bearing. This is done in order to increase the EFFECTIVITY of the wall.