In regenerative process of water gas production what fraction of total cycle time is taken by downrun operation?(a) 35%(b) 33%(c) 30%(d) 2%This question was addressed to me in an online quiz.My doubt stems from Inorganic Chemical topic in portion Inorganic Chemical Industries of Chemical Technology

Answer»

The correct option is (b) 33%

To explain I would say: 35% of total cycle time is taken by BLOW or heat up, 33% and 30% is took by downrun and uprun operation REMAINING 2% of total cycle time it took by short purge uprun operation.