List The Search Strategy That The Underlying System Uses To Determine The Requirement Types?

Answer»

The following are the pre-defined SEARCH strategy that the underlying system uses to determine the requirement types:

  1. The system uses strategy group in the MATERIAL master to find a requirement type.
  2. If the strategy group is not maintained, the system uses MRP group to determine a requirement type.
  3. If the MRP group is not defined the underlying system uses material type to determine a requirement type.
  4. If NONE of the above is found, the system follows a SPECIAL rule and tries to determine a requirement type with the help of item CATEGORY and MRP type.
  5. In case, when the MPR type is not defined the system uses only the item category to determine requirement type.

The following are the pre-defined search strategy that the underlying system uses to determine the requirement types: